a task completed by 30 persons in 4 days. in how many days, the same will be completed by 40 persons?

Respuesta :

Plasmataco
Plasmataco Plasmataco
  • 25-11-2017
Basically to solve this you do:
Time1*Worker1=Time2*Worker2
Thus Time1=4, Worker1=30, Worker2=40
4*30=40*Time2
Time2=4*30/40
Time2=3 days
Answer Link

Otras preguntas

ILL GIVE YOU BRAINLIEST PLEASE HELP MEEvidence from Miller and Urey's experiments suggest that complex organic molecules could be formed from other, simpler mol
There is a paint chip on the edge of a gear for a music box. It rotates to (−7, 3) during one song when represented graphically. What is the cosine value of thi
What is the kinetic energy of a 2995 kg truck when it moving 47 ms
Explain sp hybridization in acetylene molecule? Dr aw the structure of acetylene molecule to show the bond angle and bonding molecul ar orbitals.
how to do an introduction for an descriptive essay on your favorite restaurant
What did the nazis do with their new power ?
Use the data in the simulation to find the Ka value of HF, hydrofluoric acid
What is the value of 3 1/2 - 9 3/4
What is the quotient of 8 and 72.16
PLEASE please help me