What does the measurement tell you?

Schedule performance index

Respuesta :

Аноним Аноним
  • 21-10-2020

Answer:

how close the project is to being completed compared to the schedule/ how far ahead or behind schedule the project is, relative to the overall project

Explanation:

Answer Link

Otras preguntas

the North African Maghreb states dominated by the Atlas Mountains don not include
Find the sum: 1+2+3+ ... +9999+10000.
What is 10/56 simplified
Which statements accurately describe Elizabeth I? Choose all answers that are correct. a. She achieved fame and prestige during her short reign. b. She defeated
What might happen to the frog and the Eagle if the snake were elimanted from the food chain
Traders who traveled to the Yoruba homeland were probably most interested in obtaining _____ from the people there. a. corn b. camles c. sorghum d. art
Erica earns $11.00 per hour and works a 40 - hour workweek. She is paid time and a half for every hour worked over 40 hours during a week. Erica earned $60 5.0
Judges in a court of appeals reach their decision through a _______________________ vote. three-fourths majority minority unanimous
Use apple in a sentence.
a large country economically and politically dominating a smaller country