30 men can do a piece of work in 40 days .how long it take to complete the work if 5 men were reduced​

Respuesta :

kandelhira20
kandelhira20 kandelhira20
  • 23-02-2020

Answer:

it is from unitary method

men days

30 40

25 let(x)

now from indirect variation

25×x = 30×40

25x= 1200

x=1200÷25

x=48

so there were 48men to complete the work

Answer Link

Otras preguntas

A patient was fitted with an arm cast after fracturing her humerus. Twelve hours after the application of the cast, the patient tells the nurse that her arm hur
Fill in the missing number chains below 91999
What are the three levels of self-awareness for individuals who perform specialized tasks?
Surveillance by photo traffic control system or photo radar system a) Speed Limit Enforced b) Photo Radar Zone c) Watch for Cameras d) Speed Trap Ahead
What is a CMV gross vehicle weight rating in Pennsylvania?
The serial number of the aircraft is attached to the body of the aircraft. Where? a) Under the wing b) On the tail c) Inside the cockpit d) Along the landing ge
Individuals, businesses, organizations, and governmental entities not defined as criminal justice agencies, such as tax offices or municipal offices, are author
what fraction is equivalent to 9/12
What should friends and relatives remember when helping someone who is grieving?
Structured questions 2 Global food prices have increased significantly in recent years. Food poverty has also increased as result. In an attempt to reduce the