seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

Sara cut off 1/8 of a 48-inch piece of ribbon. Jane cut off 1/9 of a 36-inch piece of ribbon. They compared their cut pieces. Whose piece is longer? How much lo
What digit appears in the units place in the number obtained when 2^320 is multiplied out?
how do u multiply x^2-4 over x^2-1 times x+1 over x^2+2x
If there are no apples on the bush and one skis off onto the earth how many fruits are left to be drinken by the humans?
why did the Federalist Party lose support after the war of 1812
Suppose Maya made another sign with an area of 48 square inches. Would this sign be larger or smaller than the sign with an area of 48 square centimeters? Expla
what happens during vaporization and evaporation?
how to solve linear equations by substitution?5x+2y=9x+y=-3
List three impulse goods that you or someone you know has purchased
What is ( √2 - √3 )² =