Aggregate planning is capacity planning that typically covers a time horizon of one to three months. True or false?

Respuesta :

MsTeel
MsTeel MsTeel
  • 24-04-2019

Answer:

False

Explanation:

Aggregate planning is typically done 6-18 months prior to the time period it covers.

Answer Link

Otras preguntas

Why is Anatomy important in the medical field
A vacation tour company provides free guidebooks for each adult who takes one of its tours. If no more than 72 people will take the company’s tour today, of whi
Larios filled her a 5 gallon jug with water. How many times can she fill her to 2- quart canteen with water from the jug?
if you want to determine the equal annual end of year payments necessary to amortize fully $6,000,10%loan over 4 years​
A motorcycle has a speed of 30 m / s. After braking, it decelerates with constant deceleration A = -3.0 m / s ^ 2 Calculates its speed after 3.0 s
High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental prede
One more repair is needed to get the ferris wheel up and running! This one will require a cable to connect chair L to the ground, and then continue back to chai
1. True or False: If you stop using your credit card for purchases, you won't ever have to pay interest again.
Which of the following best distinguishes the Cold War era from the struggle against terrorism in the 2000s? A. The Cold War was fueled by competing economic a
brainly wont let me use question, screenshot below.