The work breakdown structure is an important tool used by the project manager and the project team for all of the following reasons except:
a. Improved communication
b. Displays dependencies for project activities
c. Improves accuracy of cost and duration estimates
d. Identifies major project deliverables
e. Provides a basis for generating the project plan

Respuesta :

Otras preguntas

An allergic reaction may increase the number of what?
I have been stuck on this question and i would like to know how to solve it ? A mother horse and a baby horse walk 10 miles from point A to point B. The mother’
Maren walks 3/5 miles in 24 minutes at a steady pace.  How long does it take her to walk 2 miles.
what forces led to the rise of the mongols?
Our galaxy contains roughly 250000000000 stars. How many billion is this?
why did people hate the roman empire
A population of 3.5 million bacteria increases by 488000 . How many bacteria are there now?
Help with problem 14?!
allen runs 8 miles in 3 hours at a steady pace.  how long does it take him to run 3 miles
Roxanne has 1/2 as many beads as Sherie. The number of beads Sherie has is 4/5 that of Marcos. Marcos has 165 beads. How many more beads does Marcos have than R