The standard cost of Product 21 includes three hours of direct labor at $12.70 per hour. During July, the company incurred 3,800
hours of direct labor at an
average rate of $13.20 per hour. It produced 1,300 units. Compute the price and quantity variances for
labor.
Labor price variance
Labor quantity variance

Relax

Respuesta :

Otras preguntas

What did the South stand to gain as a result of the Compromise?
Had you told me, I (bring) a mule. *
1. If average fixed cost is 40 and average variable cost is 80 for a given output, we then know that average total cost is
14. In a garden 746496 apple trees are arranged in such a way that, there are as inany rows as there are in a row. How many rows are there in the garden ​
Which option lists events during and after the end of apartheid in the correct order
Solve the following system of equations using the elimination method 8x + 2y= 30 7x+2y= 24 A) (3.-12) B) (-53) C) 1-6,-5) D) 16,9)
find the missing side of the triangle.​
state the term used to describe the turning force exerted by the man pushing down on a lever to lift one end of a heavy log​
A hexagonal pyramid is located ontop of a hexagonal prism. How many faces are there? A. 15 B. 24 C. 6 D. 13
How to prevent Hepatitis A?