  • 24-09-2022
  • Mathematics
contestada

A fiber optic cable company is installing cable along a road 6 1/2 miles long. The crew takes a day to install each 1/4 mile of cable. How many days will the installation take?

A fiber optic cable company is installing cable along a road 6 12 miles long The crew takes a day to install each 14 mile of cable How many days will the instal class=

Respuesta :

Otras preguntas

When did Lincoln declare that Thanksgiving would be celebrated on the last Thursday of November?
what profession has the highest rate of suicidal death
Explain how water move from cell to cell in a leaf
The first truck carries 35 tons less rice than the second truck. The number of paddy in the first truck is 2/3 of the amount in the second truck. How many tons
Which system of equations is equivalent to this system?
Different between sound wave and water wave
The coordinates of the end points of TU are T(2,4) and U(11,13)
can some one help me write a poem
True or False. A range has an address called a range address. True False
The equation for a base solution is B + H2O = BH+ + OH- The strength of the base in a solution is increased. How will the number of particles change? (1 point)